Trans-pacific Cable

Posted by admin 
Trans-pacific Cable
November 20, 2013 03:32PM
Re: Trans-pacific Cable
March 31, 2014 10:17PM
Quote

He believed the chances of that US$350m (NZ$403m) cable project going ahead were “better than 50:50”. Hawaiki’s chief executive, former Alacatel-Lucent executive Remi Galasso, moved his family to New Zealand a few months ago which Mitten took to be a sign of his commitment.

[www.stuff.co.nz]
Re: Trans-pacific Cable
June 12, 2014 01:07PM
We have received the following question:

"Does TPCABLE.2015 (and related contracts) mean the cable is physically laid in place or is operational by the required time?"

As stated in the contract, the cable simply has to be laid. It does not require the cable to be operational.
Re: Trans-pacific Cable
December 17, 2014 04:30PM
"Does TPCABLE.2016 (and related contracts) mean the new cable is "physically laid from NZ all the way (albeit via hops) to the US"? or could it be for instance "cable laid as far as Australia and then extended connectivity leased from Australia to the US on existing infrastructure"?



Edited 1 time(s). Last edit at 12/17/2014 04:32PM by horsie.
Re: Trans-pacific Cable
December 19, 2014 05:03AM
I have been wondering about Horsie's question myself. In addition, I would appreciate clarification on how this would be judged if the new cable went only to Hawaii or Guam and then connected to the mainland USA through a secondary cable. Either of those islands would fulfill the requirement "that a second fibre-optic cable is built linking New Zealand and the United States", but it would hardly seem like a true "Trans-Pacific Cable" to me.